问题描述

我们最近安装了TFS 2010,并通过利用Scrum模板以敏捷的方式使用它。我们很好奇,是否有一种方法可以在TFS中跟踪任务的截止日期,以便仅查看截止日期为昨天和/或今天的任务就可以轻松地运行我们的日常工作。

We recently installed TFS 2010 and are using it in an agile manner by taking advantage of the Scrum templates. We were curious if there is a way to track task due date within TFS so that we can easily run our daily scrums by only looking at tasks with a due date of yesterday and/or today.

推荐答案

没有截止日期字段,因为在Scrum方法中不需要此类信息。所有与sprint相关的任务(sprint待办事项)均具有sprint的截止日期。所有用户故事(产品积压项目)都没有截止日期,因为这是由业务优先级决定的,并且团队能力=>截止日期可以更改每个冲刺。

There is no due date field because in Scrum methodology such information is not needed. All sprint related tasks (sprint backlog items) have due date of sprint ending. All user stories (product backlog items) have no due date because this is driven by business priority and team capacity => due date can change every sprint.