问题描述
您好,
我在迁移在msps 2007中创建的计划时遇到了大问题到msps 2010。
I am facing enormous issues while migrating plans created in msps 2007 to msps 2010.
我在将计划从msps 2007迁移到msps 2010时有重复资源,并且实际数据没有重新分配到资源。
I am having duplicate resources while migrating plans from msps 2007 to msps 2010 and actuals are not reallocated to resources.
(附注: 在msps 2007(本地托管)中,资源是使用本地域创建的,在msps 2010中,必须使用服务器的不同域创建资源,该服务器位于数据中心。
(Side note: In msps 2007(which is locally hosted) , the resources were created using a local domain and in msps 2010 the resources must be created using a different domain for the server which is hosted in a datacenter.
遵循的步骤:
已安装msp 2010,其次是Service Pack 1和CU August 2012。
Installed msp 2010 followed by Service pack 1 and CU August 2012.
计划创建于msp 2007已在本地保存,并在msp 2010中打开并保存。
Plans created in msp 2007 have been saved locally and were opened and saved in msp 2010.
在msps 2010中发布计划后,我遇到了上述问题(重复资源)。
After publishing the plans in msps 2010; i am having the above issue(Duplicate Resources).
建议的解决方案 1:
在没有Service Pack 1的情况下安装MSPS 2010(即将安装) r迁移已经完成。)
Installing MSPS 2010 without the Service Pack 1 (to be installed after migration has been completed).
此解决方案适用于同事,但在我的情况下不起作用;在发布计划时,会给出以下错误消息:
This solution works for a collegue but it did not work in my situation; while publishing the plans, the following error msg is given:
作业类型:加载
错误ID:12015(0x2EEF)
Error ID: 12015(0x2EEF)
错误说明:发生内部错误
Error Description :An internal error occured
我需要重新安装SP1和CU,以便消除错误消息,如上所述。
I needed to reinstalled SP1 and CU so as to get eliminate the error message as described above.
建议按上述步骤进行;在安装SP1补丁之前迁移计划?它适用于同事。
Is it advisable to proceed as above; migration of plans before installing SP1 patch? It works for a collegue.
建议的解决方案2:
检查提供的msps 2010链接;事实上它已经在向后兼容模式下配置。
Check the link msps 2010 provided; infact it has been configured in Backward Compatibility Mode.
可能是计划已损坏;我尝试通过转换XML中的计划并以mpp重新导入它来恢复它。
May be the plans are corrupted; I tried to recovered it by converting the plans in XML and re-import it in mpp.
事实上我做了一个测试,我映射了提供的链接 在msp 2007中计划并在2007服务器上发布计划;没有重复的资源。
Infact I did a test, I mapped the link provided in msp 2007 plans and publish the plans on the 2007 server; there was no duplicate resource.
有人可以告诉我如何继续迁移吗?
Can anyone advise me how to proceed with the migration?
非常感谢
Soudha
推荐答案
一般来说,你有两个选择:
generally speaking you have two choices:
- 保存为mpp并导入到2010年。在这种情况下,您只需确保在2007年和2010年以完全相同的方式拼写资源名称.Project Server将资源与其新帐户匹配
- 迁移整个数据库并更改迁移到新域帐户后的帐户。
希望这会有所帮助,
Renke