如何修改TASK持续时间而不依赖于WORK分配

如何修改TASK持续时间而不依赖于WORK分配

本文介绍了2007:如何修改TASK持续时间而不依赖于WORK分配?的处理方法,对大家解决问题具有一定的参考价值,需要的朋友们下面随着小编来一起学习吧!

问题描述

我的目标是能够在运营项目中没有正常控制的情况下记录和预算项目提案。

My goal is to be able to document and budget project proposals without the controls normal in an operating project.

具体而言。  我想为任务设置日期和/或DURATION以显示建议的时间表。

Specifically.  I want to put dates and/or DURATION for task in order to show the proposed timeline.

接下来,我想将WORK分配给任务,以便我可以计算预算金额。

Next, I want to assign WORK to the task so that I can calculate a budgeted amount.

我希望能够相互独立地修改这些值。

I would like to be able modify these values independent of each other.

在完成提案时,我不希望这两个由dur * units *的'铁公式'起作用。  它在提案阶段创造了太多的工作。

While completing proposals, I do not want these two determined by the 'iron formula' of dur*units*work.  It creates too much work in the proposal stage.

任何想法?

我看到他们已经改变了对工作单位的处理2010年但是,我不确定这会给我什么......

I see that they have changed the handling of the work units in 2010 but, I am not sure that will give me what I am looking for.....

推荐答案

如果您这样做,最优雅的解决方案:升级 到Project 2010并使用手动计划的任务。这确保了你想要的一切。

Most elegant solution if you cn do it: upgrade  to Project 2010 and use manually scheduled tasks. That assures all you want.

但你可能不能: - (

But you probably can't :-(

然后转到工具,选项,计算和设置计算模式这也是这样的。

Then go to Tools, Options, Calculation, and set Calculation mode to Manual. That does it as well.

问候,


这篇关于2007:如何修改TASK持续时间而不依赖于WORK分配?的文章就介绍到这了,希望我们推荐的答案对大家有所帮助,也希望大家多多支持!

09-06 01:51