问题描述
有人可以提供帮助,因为这会让我感到困惑。
Can someone please help as this is driving me up the wall.
我们在SharePoint 2010平台上运行Project Server 2010.
We are running Project Server 2010 on a SharePoint 2010 platform.
我们不使用时间表,而是使用任务表更新资源项目,输入项目的实际剩余时间和小时数。我是大多数项目的项目经理,我有一个自动批准规则,用于批准和发布
更新。
We don't use timesheets, but instead resources update projects using the task sheet, entering actual hours and hours remaining for projects. I am the project manager for most of the projects and I have an automatic approval rule set up to approve and publish updates.
一切都已经好几个月了,但我突然遇到一个项目的问题。
Everything has been going fine for a number of months, but I am suddenly having problems with one project.
资源更新他们的任务并照常提交。然而,不是自动发布,而是将任务设置为"已接受"。已发布的数据库。
Resources update their tasks and submit as usual. However, rather than automatically publishing, the tasks sit as "accepted" on the Published database.
一旦我进入项目并进行保存和发布,实际情况将完全从项目和PWA任务单中的用户视图中消失。
Once I go in to the project and save and publish, the actuals dissapear completely from project and from the users view in the task sheet on PWA.
通过重命名项目然后保存副本作为原始项目名称,我已经完成了这一次,大约一个月,它运行良好。但是现在它再次出现了。
i have gotten round this once by renaming the project and then saving a copy as the original project name and again, for about a month, it's worked fine. But now it has gone again.
我现在已经在两个单独的项目上发生了这件事,这让我疯狂。
I have had this happen on two seperate projects now and it is driving me nuts.
任何想法都可以将是辉煌的
Any ideas at all would be brilliant
谢谢
推荐答案
你在CU级别?您可能会遇到以下问题已于2012年4月修复CU
What CU level you are at? You may be running into below issue fixed in April 2012 CU
假设您为Project Server 2010中的项目配置自动发布规则。检查项目时out,自动发布
规则不会按预期发布项目。此外,将跳过所有连续的自动发布作业,并且不会发布符合自动发布规则的其他项目。
http://support.microsoft.com/kb/2598272
谢谢,
Kiran K.
Kiran K.