Project女士显示错误的持续时间

Project女士显示错误的持续时间

本文介绍了Project女士显示错误的持续时间的处理方法,对大家解决问题具有一定的参考价值,需要的朋友们下面随着小编来一起学习吧!

问题描述

我是ms Project的新用户。我意识到持续时间有问题。它应该是3天,但它被写下来5天了。

Hi, I'm new user for ms Project. I realized there is something wrong with the duration. it should be 3 day, but it was written down 5 days instead.

有人知道如何解决这个问题吗?

does anybody know how to solve this??

我想上传我的screeshot,但我不能,因为:

i want to upload my screeshot, but it I can't, because:

正文文本无法包含图片或链接,直到我们能够验证您的
帐户

我确定我的帐户已经过验证。如何解决这个问题?

I'm sure that my account has been verified. how to solve this too?

非常感谢你。

thank you very much.

推荐答案

您是否在日历"标准"上应用了任何更改;或任务或项目的不同日历?或者您是否更改了文件中的小时/日 - 选项 - 时间表?

did you apply any changes on calendar "Standard" or a different calendar to either task or project? Or did you change Hours/Day in File - Options - Schedule?

当您输入5天时,计算为5 x"小时数"。如选项中所定义。可以预测这是40小时。然后项目检查为此任务定义的可用工作时间(如果您为此任务定义了任务日历)或项目日历(项目 - 更改工作时间)定义的

When you enter 5 days, it is calculated as 5 x "Hours by day" as defined in Options. Presumable this is 40hrs. Then project is checking the available working hours defined for this task (if you defined a Task Calendar for this task) or as defined for Project Calendar (Project - Change Working Time).

我通过为我的项目应用24小时日历获得相同的结果:

I get the same result by just applying 24hours Calendar for my project:

这可以解释你看到的内容吗?

问候

Does that explain what you see?
Regards

Barbara

Ps:不知道为什么你无法上传图片。

P.s: No idea why you can't upload images.


这篇关于Project女士显示错误的持续时间的文章就介绍到这了,希望我们推荐的答案对大家有所帮助,也希望大家多多支持!

07-30 23:27