问题描述
我正在尝试创建一个包含10个不同项目计划的高级计划计划。我在执行此操作时遇到了麻烦,因为当我将开始日期和结束日期放在不同的项目文件中时,持续时间已关闭。这是因为每个
个别项目都有指定的非工作日。这意味着我无法将它们合并到一个文件中,因为某些非工作日不适用于其他项目。现在我知道我可以创建一个自定义字段并将其命名为
而不是"duration",但这是问题所在。我将使用以下示例来演示:
I'm trying to create a high-level program plan, that incorporates 10 different project plans. I'm having trouble doing this because the durations are off when I put the start and end dates in a different project file. The reason for this is because each individual project has it's specified non-working days. This would mean that I couldn't incorporate them into a single file because some non working days aren't applicable to other projects. Now I know that I could just create a custom field and name it something other than "duration", but here's the problem with that. I'll use the following example to demonstrate:
>计划计划:34天
>摘要任务1: 24天
>Summary task 1: 24 days
>子任务: 12天
>Sub task: 12 days
>子任务: 12天
>Sub task: 12 days
>摘要任务2: 10天
>Summary task 2: 10 days
>子任务: 5天
>Sub task: 5 days
>子任务: 5天
>Sub task: 5 days
如果将这些持续时间放在自定义字段中,并且我要在摘要任务1中更改子任务的持续时间,例如,然后摘要任务1和程序计划持续时间不会改变。我确定之前有人遇到过这个问题。是否有
的解决方案?
If these durations were placed in a custom field and I were to change the duration of a sub task in summary task 1, for example, then summary task 1 and program plan durations would not change. I'm sure someone has run into this problem before. Is there a solution?