问题描述

我想使用CSOM代码在任务2上设置前置任务。前一个是"1FS + 10days" 

I want to set a Predecessor on Task 2 using CSOM code. The predecessor is "1FS + 10days" 

我目前卡住了,因为我找不到任何设置"提前期"的方法。使用CSOM。 

I am currently stuck as i can't find any way of setting "Lead time" using CSOM. 

这是关于DraftTaskLink类的MSDN页面

This is page from MSDN on DraftTaskLink Class

http://msdn.microsoft.com/en-us/library /microsoft.projectserver.client.drafttasklink_di_pj14mref_members(v = office.15).aspx

http://msdn.microsoft.com/en-us/library/microsoft.projectserver.client.drafttasklink_di_pj14mref_members(v=office.15).aspx

另一方面,似乎有可能(虽然不太确定)通过PSI

On the other hand, it seems possible (not too sure though) through PSI

http://msdn.microsoft.com/en-us/library/websvcproject.projectdataset.dependencyrow_di_pj14mref_members(v = office.15).aspx

http://msdn.microsoft.com/en-us/library/websvcproject.projectdataset.dependencyrow_di_pj14mref_members(v=office.15).aspx

这是一个限制吗CSOM?如果有的话,是否有专门提及此的文件?

Is this a limitation of CSOM ? If so, is there a documentation which specifically mention this ? 

Hammad Arif

Hammad Arif EPM Advice Blog