问题描述

我们在开发过程中有9个Sprint。

We have 9 Sprints during our development.

每个Sprint是10个工作日。

Each Sprint is 10 working days.

我们最初计划在QA(系统测试)阶段开发完成后4周(Sprint 9结束)。

We had originally planned on a QA (System Test) phase for 4 weeks after development completes (end of Sprint 9).

我们现在希望在每个Sprint结束时执行QA,而不是在Sprint 9结束时执行QA。

We are now looking to perform QA at the end of each Sprint rather than doing QA at the end of Sprint 9.

I有几个问题:

1。我们采取的方法是改变每个开发人员的容量,以便在每个Sprint中留出时间来解决引发的缺陷。这意味着我们不会在Sprint 12或13之前完成。

1. The approach we are taking is to change the capacity of each developer to allow time in each Sprint to resolve Defects raised. This will mean that we will not finish until potentially a Sprint 12 or 13.

2。我们计划在Sprint中解决关键/高优先级缺陷,并在最后使用Sprint来解决中/低优先级缺陷。

2. We are planning on addressing critical / high priority defects during our Sprints and having a Sprint at the end to resolve medium / low priority defects.

我正在寻找有关此方法的反馈/建议那些做过类似或类似事情的人可能效果更好吗?

I'm looking for feedback / advice on this approach from those who have done something similar or something different maybe which works better?




谢谢

CG

推荐答案

如果您想在每个sprint结束时执行质量检查,您可以考虑为每个sprint添加工作日。如果您的质量保证用户与开发者不同,您可以为每个成员设置休息日。让我举个例子:

If you want to perform QA at the end of each sprint, you could consider to add working days for each sprint . If your QA users are not the same people as the developer, you could set days off for each member. Let me make an example for this:

我设置Sprint5开始日期:3月30日,结束日期:4月7日,7个工作日。 3 / 30-4 / 5是开发人员的工作日。 4 / 6-4 / 7是测试工作日。我在4 / 6-4 / 7期间将jingzhu yan设置为2天。并将Starain Chen在3 / 30-4 / 5期间休息5天。

I set Sprint5 start date: March 30, end date: April 7, 7 working days. The 3/30-4/5 is developer working days. The 4/6-4/7 is tester working days. I set jingzhu yan 2 days off during 4/6-4/7. And set Starain Chen 5 days off during 3/30-4/5.

这种方法是否符合您的要求?

Could this method meet your requirement?

>大于2。我们计划在Sprint期间解决关键/高优先级缺陷,并在最后使用Sprint来解决中/低优先级缺陷。

您可以选择特定的sprint您想要的 作为关键/高优先级或中/低优先级工作项的迭代值。

You could select specific sprint which you want as the iteration value of critical/high priority or medium/ low priority work items.

最诚挚的问候


这篇关于在Sprint期间执行QA - 建议?的文章就介绍到这了,希望我们推荐的答案对大家有所帮助,也希望大家多多支持!