问题描述
我已经在EPT中附加了一个模板,并且成功地在PWA中使用该EPT创建了计划,但我无法编辑计划,除非我回到项目中心并检查该项目,这给用户带来了很多麻烦。
I have attached a template in EPT and schedule got created with that EPT in PWA succesfully, but I am not able to edit the schedule until and unless I go back to project center and check in that project, this is creating a lot of trouble for the user.
我验证了默认选项 "基本项目计划"在初始配置中,我能够做到这一点。
I verifield the default option "Basic Project Plan" that comes in initial configuration, where I am able to do this.
任何想法可能是什么原因。
Any idea what could be the reason.
推荐答案
这是否发生在所有模板上你创建或只是这个特定的?你在跑什么SP?该计划是否包含固定工作或努力驱动的任务?
Does this happen to all templates that you create or just this specific one? What SP are you running? Does the plan contain fixed work or effort-driven tasks?