问题描述

刚为企业设置O365。还激活了Project Online Premium。设置企业资源库。与Active Directory同步。一切正常。

Have just setup O365 for enterprise. Also activated Project Online Premium. Setup Enterprise Resources Pool. Synchronized with Active Directory. all that is working fine.

故障是:创建项目和任务(通过PWA)和构建团队(来自企业资源池)工作,但似乎不是任何查看(或具有自动计划)的方式都会考虑资源的O365日历。

The glitch is: creating a project and tasks (via PWA), and Building Team (from enterprise resource pool) works, but, doesn't seem to be any way to have view (or have auto-schedule) take resource's O365 Calendar into consideration.

示例:资源的日历(在O365中)显示下周的每一天预订固定。早上8点到晚上9点。

Example: A resource's calendar (in O365) shows every day next week booked solid. 8am to 9pm.

我创建了一个具有自动计划而不是手动任务的任务,分配资源,它为星期一安排资源(同一周他不可用)。

I create a task with auto schedule rather than manual for the task, assign the resource, it schedules the resource for monday (same week he's not available).

有没有办法链接PWA资源和日历,以便可以检查O365中的资源日历?

Is there a way to link PWA resources and calendars so resource's calendar in O365 can be checked?

注意:资源视图的容量规划也不反映O365日历信息对于上述资源,即使在AD与资源池重新同步并重建团队之后,容量规划可用性视图也会将此人显示为完全可用。

NOTE: Capacity Planning of Resources views as well do NOT reflect O365 calendar information so for above resource, even after a resync of AD with Resource Pool and rebuild of team, Capacity Planning Availability View shows this person as fully available.

资源"日历"选项仅显示标准。是否有办法使用资源的O365日历?或者某些后门方法将他们的O365日历同步到"标准"日历。日历?到达这里。

Resource "Calendar" option only shows Standard. Is there a way perhaps to have a resource's O365 Calendar be used? Or some back door method that sync's their O365 calendars to the "Standard" Calendar? Just reaching here.

推荐答案

您在日历之间寻找的联系Outlook和Project Online不存在。 对不起 在Project Online中,系统默认情况下会根据企业标准日历为每个资源创建日历。  Project Online中资源的
日历没有以任何方式链接到他们的Outlook日历。 如果您的组织在Project Online中使用了Timesheet功能,团队成员可以提交未来计划的非工作时间,例如休假,然后在Project Online的日历上输入
。 这是你能想到的最好的。 希望这会有所帮助。

The linkage you are seeking between calendars in Outlook and Project Online does not exist.  Sorry.  In Project Online, the system creates a calendar for each resource, based on the enterprise Standard calendar by default.  The resource's calendar in Project Online is not linked in any way to their Outlook calendar.  If your organization used the Timesheet functionality in Project Online, team members can submit future planned nonworking time, such as vacation, which will then be entered on their calendar in Project Online.  That's the best you can expect.  Hope this helps.