我正在通过MPXJ库导出MS Project中的项目,但我有一个问题:
如何将星期六(或星期日)的特定日期设置为工作日而不是周末? (在ProjectCalendar或其他地方)
例如,将2014年10月18日(星期六)设置为工作日,但另一个星期六必须是周末。

public ProjectCalendar initCalendar(ProjectFile projectfile, int calendarId, Date startDate, Date endDate) {
        ProjectCalendar defaultCalendar = projectfile.addDefaultBaseCalendar();

        /*Setup standart working week*/
        defaultCalendar.setName("Standart");
        defaultCalendar.setWorkingDay(Day.MONDAY, DayType.WORKING);
        defaultCalendar.setWorkingDay(Day.THURSDAY, DayType.WORKING);
        defaultCalendar.setWorkingDay(Day.WEDNESDAY, DayType.WORKING);
        defaultCalendar.setWorkingDay(Day.TUESDAY, DayType.WORKING);
        defaultCalendar.setWorkingDay(Day.FRIDAY, DayType.WORKING);
        defaultCalendar.setWorkingDay(Day.SATURDAY, DayType.NON_WORKING);
        defaultCalendar.setWorkingDay(Day.SUNDAY, DayType.NON_WORKING);


        ProjectCalendarHours pch;
        pch = defaultCalendar.addCalendarHours(Day.MONDAY);
        pch.addRange(ProjectCalendar.DEFAULT_WORKING_MORNING);
        pch.addRange(ProjectCalendar.DEFAULT_WORKING_AFTERNOON);

        pch = defaultCalendar.addCalendarHours(Day.THURSDAY);
        pch.addRange(ProjectCalendar.DEFAULT_WORKING_MORNING);
        pch.addRange(ProjectCalendar.DEFAULT_WORKING_AFTERNOON);

        pch = defaultCalendar.addCalendarHours(Day.WEDNESDAY);
        pch.addRange(ProjectCalendar.DEFAULT_WORKING_MORNING);
        pch.addRange(ProjectCalendar.DEFAULT_WORKING_AFTERNOON);

        pch = defaultCalendar.addCalendarHours(Day.TUESDAY);
        pch.addRange(ProjectCalendar.DEFAULT_WORKING_MORNING);
        pch.addRange(ProjectCalendar.DEFAULT_WORKING_AFTERNOON);

        pch = defaultCalendar.addCalendarHours(Day.FRIDAY);
        pch.addRange(ProjectCalendar.DEFAULT_WORKING_MORNING);
        pch.addRange(ProjectCalendar.DEFAULT_WORKING_AFTERNOON);


        /* setup holydays*/
        List<Date> workingHollidays = DBHelper.getWorkingHolidays(ppmCalendarId, startDate, endDate);
        for (Date work : workingHollidays) {
            ProjectCalendarException ex = defaultCalendar.addCalendarException(work, work);
        }

        /*There is  I need change stendart week and setup 6-days working week (Saturday is work day) */
        /*something like that*/
        Date workindDay = new SimpleDateFormat("dd.MM.yyyy").parse("18.10.2014");
        defaultCalendar.setWorkingDay(workindDay, DayType.NON_WORKING); // This code not work
        pch = defaultCalendar.addCalendarHours(workindDay); // This code not work
        pch.addRange(ProjectCalendar.DEFAULT_WORKING_MORNING);
        pch.addRange(ProjectCalendar.DEFAULT_WORKING_AFTERNOON);
    }


在Ountput中,Microsoft Project xml将像这样标记:

<Calendar>
    ...
    <WeekDay>
        <DayType>
            0
        </DayType>
        <DayWorking>
            1
        </DayWorking>
        <TimePeriod>
            <FromDate>2014-10-18T00:00:00</FromDate>
            <ToDate>2014-10-18T23:59:00</ToDate>
        </TimePeriod>
        <WorkingTimes>
            <WorkingTime>
                <FromTime>09:00:00</FromTime>
                <ToTime>13:00:00</ToTime>
            </WorkingTime>
            <WorkingTime>
                <FromTime>14:00:00</FromTime>
                <ToTime>18:00:00</ToTime>
            </WorkingTime>
        </WorkingTimes>
    </WeekDay>
    ...
</Calendar>


谢谢。

最佳答案

我找到答案了。
有将自定义日期作为工作日期的代码:

Date workindDay = new SimpleDateFormat("dd.MM.yyyy").parse("18.10.2014");
ProjectCalendarException ex = defaultCalendar.addCalendarException(workindDay, workindDay);
ex.addRange(ProjectCalendar.DEFAULT_WORKING_MORNING);
ex.addRange(ProjectCalendar.DEFAULT_WORKING_AFTERNOON);


范围的顺序很重要。

09-25 22:54